Skip to content

Illustrative deal · Shut-in wells to gas-fired power

Idle wells are stranded gas. Stranded gas is power.

Which shut-in wells in a power-constrained region can be restarted to feed on-site generation for new large loads?

Bring one question
  1. What surfaces

    A grid-congestion watch fires. Large-load interconnection requests are rising and the queue is saturated.

  2. What we evaluate

    340 idle wells screened down to a 12-well cluster near substation-adjacent parcels. Operator and mineral owner resolved. Plug-and-abandon liability quantified.

    Pursue a 12-well cluster, confidence moderate. Remaining reserves are uncertain because production history after shut-in is sparse.

  3. How it moves forward

    Operator acquisition plus gas offtake to on-site generation.

    Potential capital: Energy PE · Project-finance lender · Royalty investor.

    Actual restart rates and decline curves write back against the prediction.

20B+normalized rows, full provenance
~1,000governed data tables
249countries with source coverage
~18.8Bdistinct source records
THE CORPUS

Evidence that never guesses.

Our engine assembles public physical-world records into one governed surface. Publisher claims are tested against geographic evidence. Missing evidence stays visible; unresolved locations are not guessed. Reconciliation and source lineage make every answer traceable.

Every record carries its source. Customers govern their own use of it. Use, export and redistribution remain subject to applicable source terms.

Breadth, reconciliation, provenance.

GOVERNED DATA INFRASTRUCTURESource-traceable
Sources→Classify→Normalize→Register→Reconcile→Score
Parcels, wells, water rights, mineral records, broadband, logistics, environmental liabilities, air and emissions. Coverage and source dates are stated per engagement.
TEN SENSING DOMAINS

Ten ways to see a physical asset.

Each domain combines authoritative sources, domain-specific scoring, geospatial intelligence, owner resolution and distress detection. An asset can rank high in several at once, and those overlaps are where layered origination lives.

TIER 1 · ENERGY & INFRASTRUCTURE REUSE
Oil & gas reactivationIdle, shut-in and marginal wells scored for reactivationEXIT PATHS · OPERATOR ACQUISITION · GAS MONETIZATION · P&A TRANSFER · GEOTHERMAL
Mineral deposit intelligenceGlobal deposits scored on quality, viability, infrastructure, ownershipEXIT PATHS · ROYALTY ORIGINATION · BROWNFIELD REPOSITIONING
TIER 2 · ALTERNATIVE-USE INFRASTRUCTURE
Stranded infrastructure reuseMarginal assets scored for data-center, SMR, geothermal and microgrid reuseEXIT PATHS · POWER AND COOLING · SMR THERMAL INPUT · GRID SERVICES
Water rights & industrial riskAvailability, seniority, distress and co-location, mapped globallyEXIT PATHS · CREDIT RISK · INSURANCE · FACILITY WATER SECURITY · REMEDIATION
TIER 3 · DIGITAL & SUPPLY-CHAIN INFRASTRUCTURE
Fiber routing & broadbandRoutes, coverage gaps and subsidy eligibilityEXIT PATHS · TELECOM M&A · ISP ACQUISITIONS · RURAL COMPUTE
Agricultural supply chainProcessors, cold chain, logistics and water stressEXIT PATHS · PROCESSOR M&A · COLD-CHAIN FINANCE · SUPPLY-CHAIN CREDIT
Physical route fragilityBridges, rail crossings and multimodal chokepointsEXIT PATHS · RESILIENCE INVESTMENT · INFRASTRUCTURE BONDS
Environmental liability conversionContaminated and stranded assets turned into transactionsEXIT PATHS · BROWNFIELD REDEVELOPMENT · REMEDIATION FUNDING · CARBON
TIER 4 · PARCEL, AIR & SITING
Parcel & cadastral ownershipBoundaries, ownership, land value and assembly potentialEXIT PATHS · LAND ACQUISITION · SITE ASSEMBLY · LAND BANKING
Air, carbon & sitingEmissions, carbon, CCS pore space and renewable sitingEXIT PATHS · CARBON MONETIZATION · CCS SITING · SOLAR AND WIND SCREENING
CONVERGENCE

Count each asset once. Keep every path.

The same site can be a well, a parcel, a water constraint and a power-reuse opportunity at once. SignalPattern detects when domains describe the same asset, de-overlaps the value, and preserves every exit path, so the pipeline is ranked by real options, not double counting.

VALUE-AT-HANDOne de-overlapped figure, decomposable to any country, domain or asset
FORWARD LAYERProjected over time from decades of commodity and production history
WHAT-IFCausal counterfactual scenarios on demand
CONVERGENCE · ONE ASSET, MANY READINGSDe-overlap
A wellA parcelA water constraintA fiber-adjacent siteA power-reuse opportunity
ONE ASSET · COUNTED ONCEEvery exit path keptRanked by the number and quality of viable monetization paths. Grounded economics separated from proxy economics. Source gaps become data-acquisition tasks.
OWNER & OUTREACH GRAPH

A ranked site is useful. A site with an owner is a deal.

Assets resolve to owners, operators and contacts, linked parcel-to-owner and asset-to-owner, with an evidence package and a prioritized outreach path.

THE SIGNALConstrained load, scarce capacity
THE SEARCHPower · water · land · fiber
THE RESOLVEOwner and control path defined
THE OUTPUTFuture state, blockers, who to call

The site is not a dot. It is a financeable path.

OWNER & OUTREACH GRAPH · FLOW
1Demand signalwhat the market needs
2Domain searchenergy, water, fiber, land
3Constraint filteringcleared together
4Convergence & scoringhigh on several domains
5Owner resolutionparcel-to-owner, operators
6Diligence packagethesis, evidence, who to call
GOVERNED ·EVIDENCE PACKAGEDPROVENANCE KEPT

One loop. Three products.

Same reasoning stack, same evidence chain, same governance. Use one, or close the loop from the first signal to funded capital.

STRATEGYShould we make the bet?Explore Strategy →
ORIGINATIONYOU ARE HEREWhere can the bet land?Start with Origination →
CAPITALWho should fund the bet?Explore Capital →

Start with one site question.

Bring a live demand signal: the load, the region, the constraints. We return ranked, owner-resolved sites with the evidence behind each one.

Small to start. Proof before scale.
Bring one site questionSign in

Illustrative deal · Retired plant reuse for new firm power

A retired plant already has the hardest thing to get: a grid connection.

Which retired or marginal generation sites have interconnection and cooling that new firm power can reuse?

  1. What surfaces

    Watches on retirement announcements and firm-power procurement fire.

  2. What we evaluate

    Sites with an existing interconnect, water and land. Owners resolved.

    Pursue one site: a phased microgrid first, then an advanced-nuclear evaluation.

  3. How it moves forward

    Development equity plus project finance.

    Potential capital: Infrastructure fund · Strategic developer · Energy investor.

    Permitting and interconnection timelines write back.